UPDATE: SEPTEMBER 18TH 2019

The Building was ordered on 28th August 2019 and is expected to be delivered either the 4th or 11th November.

Between now and the arrival of the building, all the groundworks need to be completed. The contractor has been agreed and a purchase order sent for work comprising:

Foundations, soakaway and groundwater, plinths, Service connections, surfaces and water supply.

We think this will start during the first week of October… the countdown begins!